The following pictures of Taman Naga Emas MRT station were taken during the construction. Click to view from beginning.
📅 December 2022
Overview of the station and external works completion at the Taman Naga Emas MRT Station.
Overview of the at grade park and ride for Taman Naga Emas MRT Station.
Testing train works in progress at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 November 2022
Covered walkway and drop-off/pick-up passengers area for bus and taxi completed at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 October 2022
Enhancement works completed at the Taman Naga Emas MRT Station Entrance A.
Credits: mymrt.com.my.
📅 September 2022
Testing and commissioning of Automatic Fare Collection gate system in progress at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 August 2022
Repainting piers in progress at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 July 2022
View of the Taman Naga Emas MRT Station showing the completed high level pedestrian crossing.
Credits: mymrt.com.my.
📅 June 2022
View of the platform bench delivered at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 May 2022
Aerial view of the Taman Naga Emas MRT Station showing the station external works completed.
Additional pedestrian high level crossing in progress at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 April 2022
Installation of directional signages and information board maps completed at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 March 2022
Aerial view of the Taman Naga Emas MRT Station showing the station external works is completed.
Testing and commissioning of Automatic Fare Collection gate system in progress at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 February 2022
View of the completed Control Room with furnitures and equipments at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 January 2022
Ticket Vending Machine installed at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 December 2021
Aerial view of the Taman Naga Emas MRT Station showing the external infra works have been completed.
Modification walkway ramp works in progress as commended by Dewan Bandaraya Kuala Lumpur during the Certificate of Completion and Compliance (CCC) inspection at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 November 2021
Installation of Automatic Fare Collection in progress at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 October 2021
Aerial view of the Taman Naga Emas MRT Station showing the external infra works completed.
Aerial view of the underpass near KL-Seremban Highway showing the underpass crossing underneath the highway completed.
Ticketing vending machine installed at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 August 2021
Aerial view of the completed external infra works of Taman Naga Emas MRT Station.
Mural paint works completed at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 July 2021
Aerial view of the Taman Naga Emas MRT Station showing the external infra works completed.
View of the Taman Naga Emas MRT Station lift mural paint works completed.
Credits: mymrt.com.my.
📅 January 2021
Tiling and Automatic Platform Gate works in progress at the platform level of the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 December 2020
Aerial view of the Taman Naga Emas MRT Station showing the road works in progress.
Credits: mymrt.com.my.
📅 September 2020
View of the track slab cast at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 August 2020
Platform boombox installation in progress inside the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 July 2020
Rail track leading to Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 June 2020
Ongoing installation façade works for the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 May 2020
Aerial view of the Taman Naga Emas MRT Station site showing the installation of façade and roofing sheeting in progress.
Credits: mymrt.com.my.
📅 March 2020
Block wall for architecture finishing for riser next to the lift core in progress at Taman Naga Emas MRT Station platform level.
Credits: mymrt.com.my.
📅 February 2020
Aerial view of the ongoing installation of façade and roof sheeting at the Taman Naga Emas MRT Station site.
View of inside the Taman Naga Emas MRT Station showing the installation of façade cladding in progress.
Credits: mymrt.com.my.
📅 January 2020
Installation of external façade at Customer Service Office room in progress at Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 December 2019
Installation of steel structure and roof sheeting in progress at the Taman Naga Emas MRT Station site.
View of the ongoing lift shaft structure at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 November 2019
Aerial view of the Taman Naga Emas MRT Station site showing the installation of steel structure and roof sheeting in progress.
Credits: mymrt.com.my.
📅 September 2019
Aerial view of the Taman Naga Emas MRT Station site showing the station platform level works in progress.
Ongoing work at the Taman Naga Emas MRT station
Credits: mymrt.com.my.
📅 August 2019
Aerial view of the Taman Naga Emas MRT Station site showing the station intermediate level works in progress.
Credits: mymrt.com.my.
📅 June 2019
Aerial view of the permanent noise barrier installation and station concourse works in progress at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 May 2019
Ongoing launching of segmental box girder and station concourse works at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 April 2019
Aerial view of the launching of segmental box girder and station concourse works at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 March 2019
Ongoing segmental box girder launching works and station concourse works at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 February 2019
Aerial view of works in progress for station concourse and segmental box girder launching at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 January 2019
Trestle system preparation for segmental box girder launching in progress at the Taman Naga Emas MRT Station site.
Ongoing piled slab and reinforced concrete U-trough slab works at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 December 2018
Piled slab works in progress at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 Movember 2018
Segmental box girder launching using trestle system at the Taman Naga Emas MRT Station site.
Launching of segmental box girder and piled slab in progress at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 September 2018
Aerial view of segmental box girder launching at the Taman Naga Emas MRT Station site.
Segmental box girder launching at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 August 2018
Aerial view of portal beam construction and erection of launching gantry at the Taman Naga Emas MRT Station.
Erection of launching gantry at the Taman Naga Emas MRT Station site.
Credits: mymrt.com.my.
📅 July 2018
Aerial view of the portal beam works and erection of launching gantry at the Taman Naga Emas MRT Station site.
Aerial view of portal beam construction works at the Taman Naga Emas MRT Station.
Credits: mymrt.com.my.
📅 October 2017
Earthworks in progress for viaduct alignment at the upcoming Taman Naga Emas Station site.
Bored piling works in progress at the upcoming Taman Naga Emas Station site.
Credits: mymrt.com.my.
Hawk-eye View
Location of Taman Naga Emas MRT Station and its surrounding area.