The following pictures of Serdang Jaya MRT station taken during the construction. Click to view from beginning.
📅 December 2022
Overview of the station and external works completion at the Serdang Jaya MRT Station.
Installation of covered walkway at the Serdang Jaya MRT Station completed.
Credits: mymrt.com.my.
📅 November 2022
Testing and commissioning of Automatic Fare Collection gate system in progress at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 October 2022
Enhancement works in progress at the Serdang Jaya MRT Station Entrance A.
Credits: mymrt.com.my.
📅 September 2022
Serdang Jaya MRT Station external works completed.
Platform bench delivered to the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 August 2022
Installation of the Ticket Vending Machine completed at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 July 2022
Station external works completed at the Serdang Jaya MRT Station.
Installation of directional signages and information board maps completed at the entrance of the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 June 2022
Final defects and touch-up works in progress at Entrance B of the Serdang Jaya MRT Station in preparation for Agensi Pengangkutan Awam Darat Pemeriksaan Cermat Akhir inspection.
Installation of ticket vending machine is completed at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 May 2022
External works station completed at the Serdang Jaya MRT Station.
Rectification and testing works for Automatic Platform Gate system in progress at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 April 2022
Slab defect rectification works in progress at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 March 2022
Arial view of the Serdang Jaya MRT station.
Credits: mymrt.com.my.
📅 February 2022
Testing and commissioning of Automatic Fare Collection gate system in progress at the Serdang Jaya MRT Station. Jalan UPM (UPM) Aerial view of the UPM MRT Station showing the rectification of defects in progress.
Credits: mymrt.com.my.
📅 January 2022
Aerial view of the Serdang Jaya MRT Station showing housekeeping and handover preparation works in progress.
Testing and commissioning of access control system in progress at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 December 2021
Aerial view of the Serdang Jaya MRT Station showing the landscaping and monsoon drain finishing works in progress.
Installation of ticketing vending machine works in progress at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 November 2021
Aerial view of the Serdang Jaya MRT Station showing the completed external and roadworks.
Touch-up works in progress at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 October 2021
Aerial view of the Serdang Jaya MRT Station showing the road median screeding and road signage installation works in progress.
Escalator testing in progress at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 September 2021
Testing and commissioning of electrical and mechanical components at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 August 2021
Aerial view of the Serdang Jaya MRT Station showing the road premix and at grade noise barrier works in progress.
Installation of Automatic Fare Collection in progress at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 March 2021
Aerial view of the Serdang Jaya MRT Station showing external architecture works finishes.
External architecture works finishes at the Serdang Jaya MRT Station.
Credits: mymrt.com.my.
📅 August 2020
Aerial view of the Serdang Jaya MRT Station site showing the roof installation works in progress.
Purlin installation works in progress at the Serdang Jaya MRT Station site.
Credits: mymrt.com.my.
📅 September 2020
Aerial view of the Serdang Raya Utara MRT Station showing the steel structure installation works, reinforced concrete works, pedestrian overhead bridge and Entrance B.
Credits: mymrt.com.my.
📅 July 2020
Aerial view of the Serdang Jaya MRT Station site showing the roof steelwork erection in progress.
Sub structure works in progress at the Serdang Jaya MRT Station site.
Credits: mymrt.com.my.
📅 June 2020
Lower truss installation works in progress at the Serdang Jaya MRT Station site.
Aerial view of the Serdang Jaya MRT Station site showing the steelwork corbel and lower truss installation in progress.
Credits: mymrt.com.my.
📅 May 2020
Aerial view of the Serdang Jaya MRT Station site showing the concourse level architectural works in progress.
Credits: mymrt.com.my.
📅 March 2020
Ongoing station structure works at the Serdang Jaya MRT Station site.
Credits: mymrt.com.my.
📅 February 2020
Aerial view of the finishing works at utilities building and construction of station platform at the Serdang Jaya MRT Station
Credits: mymrt.com.my.
📅 January 2020
Architecture works in progress at the Serdang Jaya MRT Station concourse level.
Credits: mymrt.com.my.
📅 December 2019
Aerial view of the Serdang Jaya MRT Station showing the reinforced concrete slabs for system and non-system rooms in progress.
Architecture works in progress at the Serdang Jaya MRT Station site.
Credits: mymrt.com.my.
📅 November 2019
Ongoing construction of Serdang Jaya MRT Station concourse level.
Credits: mymrt.com.my.
Hawk-eye View
Location of Serdang Jaya MRT Station and its surrounding area.
★ ★ Back to Serdang Jaya MRT station.