The following pictures of Hospital Kuala Lumpur MRT station taken during the construction. Click to view from beginning.
📅 December 2022
View of the concourse level at Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 November 2022
Completed ground surface works at the Hospital Kuala Lumpur MRT Station.
Completed works of the platform level within the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 October 2022
Ongoing turfing and rectification works at the Hospital Kuala Lumpur MRT Station ground level.
The Security Control Room at the concourse level of the Hospital Kuala Lumpur MRT Station has been completed and handed over to Rapid Rail.
Credits: mymrt.com.my.
📅 September 2022
Above ground works at the Hospital Kuala Lumpur MRT Station completed at the Entrance B & C. Also, view of the ongoing reinstatement works at the Entrance A.
View of the completed reinforced concrete structure, architecture finishes and escalator installation from plantroom level to platform level of the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 August 2022
Completed external works at the surface level of the Hospital Kuala Lumpur MRT Station while site laydown removal works in progress.
Completed architecture finishes at the concourse level of the unpaid and paid area of the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 July 2022
Ongoing turfing and roadworks at the Hospital Kuala Lumpur MRT Station ground surface.
Completed architecture finishes at the Hospital Kuala Lumpur MRT Station platform level.
Credits: mymrt.com.my.
📅 June 2022
Ongoing road and walkway reinstatement works along Jalan Tun Razak and Jalan Kuantan of the Hospital Kuala Lumpur MRT Station.
Customer Service Room is completed and systems testing is in progress at the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 May 2022
Completed building structure and ongoing turfing works at the Hospital Kuala Lumpur MRT Station.
View of the completed escalator and architectural finishes from Hospital Kuala Lumpur MRT Station platform to roof levels.
Credits: mymrt.com.my.
📅 April 2022
Overview of the completed road construction and the ongoing external works and architectural finishes at the Hospital Kuala Lumpur MRT Station.
Completed travelators installation and architectural finishes along Adit A underpass of the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 March 2022
Automatic Fare Collection gates installation completed at the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 February 2022
Aerial view of the Hospital Kuala Lumpur MRT Station showing the completion of entrance building and ongoing external and surface works.
Aerial view of the Hospital Kuala Lumpur MRT Station showing the completion of entrance building and ongoing external and surface works.
Credits: mymrt.com.my.
📅 January 2022
Aerial view of the Hospital Kuala Lumpur MRT Station showing the entrances reinforced concrete structures completed and ongoing external painting and plastering works.
Concourse level ceiling works in front of house Customer Service Office room area completed at the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 December 2021
Construction of the Hospital Kuala Lumpur MRT Station in progress.
Aerial view of the Hospital Kuala Lumpur MRT Station showing the ongoing external finishes at the Entrance B and C of the building.
Completed Architectural Builders Works and Finishes (ABWF) at the Customer Service Office Room and ongoing systems works at the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 November 2021
View inside the Hospital Kuala Lumpur MRT Station showing the completed ceiling and cladding installation at the platform level.
Credits: mymrt.com.my.
📅 October 2021
Ongoing plastering works at the Entrance B and C with external works preparation while reinforced works in progress at the Entrance A of the Hospital Kuala Lumpur MRT Station.
Tiling works completed with the ceiling works in progress at the concourse level Adit A of the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 August 2021
Aerial view of the Hospital Kuala Lumpur MRT Station showing the completion of reinforced structure at the Entrance B and C with ongoing reinforced works at Adit and Entrance A.
Completion of wall cladding, ceiling and tiling installation at the Hospital Kuala Lumpur MRT Station platform level.
Credits: mymrt.com.my.
📅 July 2021
Aerial view of the ongoing reinforced concrete rebar works of the Entrance and Vent C Building of the Hospital Kuala Lumpur MRT Station.
Installation of the electrical containment at Low Voltage Room in plantroom level of the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 May 2021
View of Hospital Kuala Lumpur MRT Station Entrance B reinforced concrete wall rebar and formwork installation in progress.
Credits: mymrt.com.my.
📅 April 2021
View of the Hospital Kuala Lumpur MRT Station showing the ongoing construction works for reinforced concrete box.
Credits: mymrt.com.my.
📅 March 2021
Aerial view of the Hospital Kuala Lumpur MRT Station showing the Entrance B reinforced concrete construction such as slab and wall at the entrance and ground levels in progress.
Credits: mymrt.com.my.
📅 February 2021
Ongoing rebar works for reinforced concrete wall construction in Extra Low Voltage Riser at Hospital Kuala Lumpur MRT Station platform level.
Credits: mymrt.com.my.
📅 December 2020
Aerial view of the Hospital Kuala Lumpur MRT Station showing the reinforced concrete construction works in progress at the Entrance B.
Credits: mymrt.com.my.
📅 November 2020
Aerial view of the Hospital Kuala Lumpur MRT Station showing the civil and structural, architectural builders works and finishes and mechanical, electrical and plumbing in progress from platform level to concourse level Entrance B ground slab construction.
Credits: mymrt.com.my.
📅 October 2020
Aerial view of the Hospital Kuala Lumpur MRT Station.
Ongoing reinforced concrete wall reinforcement installation of the platform level of the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 September 2020
Aerial view of the Hospital Kuala Lumpur MRT Station site showing the ongoing reinforced concrete construction below ground and excavation works for Entrance B.
Ongoing reinforced concrete segment box 1 & 2 for Adit A box jacking works of the Hospital Kuala Lumpur MRT Station site.
Credits: mymrt.com.my.
📅 August 2020
Aerial view of the Hospital Kuala Lumpur MRT Station site showing the ongoing construction for vertical structures inside station and work preparation for entrances.
Ongoing reinforced concrete column rebar works at the platform area of the Hospital Kuala Lumpur MRT Station site.
Credits: mymrt.com.my.
📅 July 2020
Aerial view of the Hospital Kuala Lumpur MRT Station site showing the reinforced concrete platform slab construction, architecture works and electrical and mechanical works in progress.
Installation formwork and shoring for Overhead Track Exhaust construction at the Hospital Kuala Lumpur MRT Station site.
Credits: mymrt.com.my.
📅 June 2020
Platform reinforced slab and wall construction at the Hospital Kuala Lumpur MRT Station site.
Platform reinforced slab and wall construction at the Hospital Kuala Lumpur MRT Station site.
Credits: mymrt.com.my.
📅 May 2020
View of Hospital Kuala Lumpur MRT Station Entrance A next to Istana Budaya and Jalan Tun Razak showing excavation works for upcoming box jacking works.
Credits: mymrt.com.my.
📅 March 2020
Aerial view of the Hospital Kuala Lumpur MRT Station site showing the fabrication works at bar bending yard for station reinforcement concrete works at plantroom slab and base slab.
Construction of reinforcement concrete double slab for the retail room at the Hospital Kuala Lumpur MRT Station concourse level.
Credits: mymrt.com.my.
📅 February 2020
Reinforced concrete rebar works and ongoing cleaning for plantroom slab at the Hospital Kuala Lumpur MRT Station site.
Aerial view of the casting through Hospital Kuala Lumpur MRT Station opening for reinforced concrete works at plantroom slab.
Credits: mymrt.com.my.
📅 January 2020
Aerial view of the Hospital Kuala Lumpur MRT Station site showing the ongoing plantroom slab reinforced concrete works at station box.
Station base slab excavation removal and back-filling above station roof slab at the Hospital Kuala Lumpur MRT Station site.
Credits: mymrt.com.my.
📅 December 2019
Aerial view of the Hospital Kuala Lumpur MRT Station site showing the ongoing construction works.
Ongoing reinforced concrete construction at plantroom slab level of the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 November 2019
Ongoing construction of final concourse reinforced concrete slab panel at the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 October 2019
Aerial view of the Hospital Kuala Lumpur MRT Station site showing ongoing backfilling works above roof slab and removal of excavated soil from plantroom level.
Rectification works at soffit reinforce concrete roof slab and completed concourse slab at the Hospital Kuala Lumpur MRT Station site.
Credits: mymrt.com.my.
📅 September 2019
Night view of Hospital Kuala Lumpur MRT Station site showing reinforced concrete wall construction.
Excavation at the Hospital Kuala Lumpur MRT Station concourse level for reinforced concrete slab.
Credits: mymrt.com.my.
📅 July 2019
View of the construction works for reinforced concrete at Hospital Kuala Lumpur MRT Station Entrance C roof slab.
Credits: mymrt.com.my.
📅 June 2019
View of the installation works of reinforcement for reinforced concrete at roof slab of the Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 May 2019
Aerial view of the construction works for station box reinforced concrete wall at roof slab of Hospital Kuala Lumpur MRT Station
Station box reinforced concrete slab construction at roof slab of Hospital Kuala Lumpur MRT Station.
Credits: mymrt.com.my.
📅 April 2019
Aerial view of the ongoing activities at Hospital Kuala Lumpur MRT Station roof slab level.
Progressive station box construction taking place at the Hospital Kuala Lumpur MRT Station site.
Credits: mymrt.com.my.
📅 March 2019
Reinforced concrete works in progress at the Hospital Kuala Lumpur MRT Station site.
Aerial view of the Hospital Kuala Lumpur MRT Station site showing the ongoing construction of secant piles walls.
Full enclosure of concreting works steadily progressing at the Hospital Kuala Lumpur Station site.
Installation lean concrete works in progress at the Hospital Kuala Lumpur MRT Station site.
Credits: mymrt.com.my.
📅 February 2019
Aerial view of site demobilisation works at the Hospital Kuala Lumpur MRT Station site.
Overhead view of the Hospital Kuala Lumpur MRT Station site showing progress of Secant Bore Pile installation works at Adit A.
Polyurethane installation activities at the Hospital Kuala Lumpur MRT Station site.
Aerial view of ongoing lifting works at the Escape Shaft 3 site.
Credits: mymrt.com.my.
📅 January 2019
Preparation works to mine northbound tunnel from the Hospital Kuala Lumpur MRT Station site crossover towards Ampang Park MRT Station site.
Ongoing excavation works at the ground level of the Hospital Kuala Lumpur MRT Station site.
Credits: mymrt.com.my.
📅 December 2018
Overhead view of the Hospital Kuala Lumpur MRT Station construction site.
Wet speed mixing installation activities at the Hospital Kuala Lumpur MRT construction site.
Credits: mymrt.com.my.
📅 November 2018
Bird’s-eye view of the Hospital Kuala Lumpur MRT Station site with diaphragm wall construction works and wet soil mixing activities.
Credits: mymrt.com.my.
📅 July 2018
Arial view of the Hospital Kuala Lumpur MRT station and its surrounding.
Credits: mymrt.com.my.
📅 June 2018
Credits: mymrt.com.my.
Hawk-eye View
Location of Hospital Kuala Lumpur MRT Station and its surrounding area.
★ ★ Back to Hospital Kuala Lumpur MRT station.