The following pictures of Cyberjaya City Centre MRT station taken during the construction.
Click to view from beginning.
📅 December 2022
Overview of the station and external works completion at the Cyberjaya City Centre MRT Station.
Testing for Automatic Fare Collection system in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 November 2022
Testing train works are in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 October 2022
Trial run for Rapid Bus at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 September 2022
Enhancement works in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 August 2022
Rectification works for authority inspection readiness at the Cyberjaya City Centre MRT Station
Testing and commissioning of Automatic Fare Collection gate system in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 July 2022
Testing of ticket vending machine system in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 July 2022
Platform bench inspection for final position in progress at the Putrajaya Sentral MRT Station.
Credits: mymrt.com.my.
📅 June 2022
Aerial view of the Cyberjaya City Centre MRT Station showing the authority inspection in progress.
Touch-up and cleaning works at the Pedestrian Overhead Bridge in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 May 2022
Testing and commissioning of Automatic Fare Collection gate system in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 April 2022
Aerial view of the Cyberjaya City Centre MRT Station showing the external roadworks and landscape works in progress.
Covered walkway and drop off or pick up passenger area for bus and taxi are completed at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 March 2022
Testing of telecommunication in Telecommunication Equipment Room in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 February 2022
Overview of the Cyberjaya City Centre MRT Station and external works completion.
Testing and commissioning of Automatic Fare Collection gate system in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 January 2022
Construction of walkway in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 December 2021
Aerial view of the Cyberjaya City Centre MRT Station showing the external works in progress such as drainage works and BOMBA access.
Testing for Automatic Fare Collection system in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 November 2021
Aerial view of the Cyberjaya City Centre MRT Station showing the external works such as sewerage, drainage and roadworks are in progress.
Credits: mymrt.com.my.
📅 Ocrtober 2021
Aerial view of the Cyberjaya City Centre MRT Station showing the external works such as road, drainage, walkway and other works in progress.
Rectification works in progress at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 September 2021
Installation of Automatic Fare Collection completed at the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 August 2021
Aerial view of the Cyberjaya City Centre MRT Station showing the aluminium louvers in progress below the concourse level while drainage works and roadworks in progress.
Ongoing micro pile activity for foundation link bridge of the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 April 2021
View inside the Cyberjaya City Centre MRT Station showing the ticket vending machine installation in progress.
Credits: mymrt.com.my.
📅 May 2021
Aerial view of the Cyberjaya City Centre MRT Station showing the aluminium composite panel roof installation works in progress.
View of the Cyberjaya City Centre MRT Station showing the scupper drain, tiling and platform level in progress.
Credits: mymrt.com.my.
📅 March 2021
Aerial view of the Cyberjaya City Centre MRT Station showing roof aluminium composite panel installation works in progress.
Credits: mymrt.com.my.
📅 February 2021
Aerial view of the Cyberjaya City Centre MRT Station showing ongoing roof aluminium composite panel installation works.
Escalator accessories installation in progress at the Cyberjaya City Centre MRT Station
Credits: mymrt.com.my.
📅 January 2021
Aerial view of the Cyberjaya City Centre MRT Station site showing external painting works and reinforced concrete wall in progress.
Mural painting in progress at the external wall of the Cyberjaya City Centre MRT Station.
Credits: mymrt.com.my.
📅 December 2020
Aerial view of the Cyberjaya City Centre MRT Station showing the tiling installation works in progress at platform and concourse levels as well as mural painting works, façade works at main station and entrance architectural and mechanical and electrical works in progress.
Credits: mymrt.com.my.
📅 October 2020
Floor screeding for tiling works at the Cyberjaya City Centre MRT Station entrance.
Credits: mymrt.com.my.
📅 September 2020
Aerial view of the Cyberjaya City Centre MRT Station site showing the station box and entrance roof completed.
Credits: mymrt.com.my.
📅 August 2020
Aerial view of the Cyberjaya City Centre MRT Station site showing the entrance almost completed and façade works in progress.
Credits: mymrt.com.my.
📅 July 2020
Entrance steel structure in progress and escalators at entrance installed at the Cyberjaya City Centre MRT Station site.
Aerial view of the Cyberjaya City Centre MRT Station site showing the roof covering near completion at station box and entrance steel structure in progress.
Credits: mymrt.com.my.
📅 June 2020
Aerial view of the Cyberjaya City Centre MRT Station site showing the ongoing rooftop façade.
Credits: mymrt.com.my.
📅 May 2020
Exit staircase reinforced concrete works almost completed at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 March 2020
Aerial view of the roof covering installation at the Cyberjaya City Centre MRT Station site.
Façade steel structure installation in progress at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 February 2020
Aerial view of the installation of steel structure for façade in progress at the Cyberjaya City Centre MRT Station site
Credits: mymrt.com.my.
📅 January 2020
Ongoing roofing works at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 December 2019
Aerial view of the installation works for roof truss in progress at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 October 2019
Ground view of the Cyberjaya City Centre MRT Station site showing the works at entrance, ground floor and staircase.
Aerial view of the Cyberjaya City Centre MRT Station showing the roof steel structure in progress.
Credits: mymrt.com.my.
📅 September 2019
Aerial view of the Cyberjaya City Centre MRT Station showing the completed station platform.
Steel structure erection in progress at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 August 2019
Aerial view of the Cyberjaya City Centre MRT Station showing the completed concourse and intermediate level while platform for post tensioning beam in progress.
Platform for post tensioning beam works in progress at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 July 2019
Aerial view of the Cyberjaya City Centre MRT Station platform slab in progress.
Credits: mymrt.com.my.
📅 June 2019
View of the ongoing intermediate level slab construction works at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 May 2019
Parapet construction works completed at the Cyberjaya City Centre MRT Station north bound site.
Aerial view of the ongoing installation works for parapet at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 April 2019
Traction power substation works in progress at the Cyberjaya City Centre MRT Station site.
View of trestle erection works at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 March 2019
Segmental box girder launching works completed at the Cyberjaya City Centre MRT Station site.
View of the Cyberjaya City Centre MRT Station concourse slab.
Credits: mymrt.com.my.
📅 February 2019
Aerial view of the segmental box girder launching at the Cyberjaya City Centre MRT Station site.
Ground view of the segmental box girder launching in progress at the Cyberjaya City Centre MRT Station site
Credits: mymrt.com.my.
📅 January 2019
Ongoing segmental box girder launching works at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 November 2018
View from above of the segmental box girder launching works at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 October 2018
Aerial view of segmental box girder launching at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 September 2018
Aerial view of the Cyberjaya City Centre MRT Station site.
Completion of first span launching works at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 August 2018
Aerial view of the segmental box girder launching at the Cyberjaya City Centre MRT Station site.
Installation of launching gantry at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 July 2018
Aerial view of cross beam and pier head construction at the Cyberjaya City Centre MRT Station site.
Launching gantry assembly completed at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
📅 June 2018
Construction of pier head and cross beam at the Cyberjaya City Centre MRT Station site.
Credits: mymrt.com.my.
Hawk-eye View
Location of Cyberjaya City Centre MRT Station and its surrounding area.
★ ★ Back to Cyberjaya City Centre MRT station.