The following pictures of Metro Prima MRT station taken during the construction. Click to view from beginning.
📅 October 2021
Aerial view of the Metro Prima MRT Station showing the rectification works for defects list in progress.
Aerial view of the Multi Storey Park and Ride for Metro Prima MRT Station showing rectification works for defects list in progress
Mural painting at the Pedestrian Overhead Bridge completed at the Metro Prima MRT Station
Credits: mymrt.com.my.
📅 September 2021
Testing of ticketing vending machine system at the Metro Prima MRT Station.
Credits: mymrt.com.my.
📅 August 2021
Aerial view of the Metro Prima MRT Station.
Aerial view of the Multi Storey Park and Ride for Metro Prima MRT Station.
View of the Metro Prima MRT Station showing the floor epoxy paint works completed.
Credits: mymrt.com.my.
📅 July 2021
Aerial view of the Metro Prima MRT Station.
View of the concourse level at Metro Prima Station.
Credits: mymrt.com.my.
📅 April 2021
Aerial view of the Metro Prima MRT Station multi-storey park and ride showing external and painting works in progress. Credits: mymrt.com.my.
View inside the Metro Prima MRT Station showing the site cleaning in progress for handing over to the operator, Rapid Rail.
📅 March 2021
Aerial view of multi-storey park and ride for Metro Prima MRT Station showing the roof installation works in progress.
Credits: mymrt.com.my.
📅 January 2021
Aerial view of the Multi-Storey Park and Ride for Metro Prima MRT Station showing the ramp and staircase works in progress.
Internal mural painting works completed at the Metro Prima MRT Station.
Credits: mymrt.com.my.
📅 December 2020
Aerial view of the Multi-Storey Park and Ride for Metro Prima MRT Station showing the ramp and staircase works in progress.
Structural works such as beam and slab installation in progress for Level 3 at the Metro Prima MRT Station Multi-Storey Park and Ride.
Credits: mymrt.com.my.
📅 November 2020
View of the Metro Prima MRT Station showing the landscape, road and drainage works in progress. Credits:
Formwork and rebar installation works in progress at the Multi-Storey Park and Ride Metro Prima MRT Station.
📅 July 2020
Aerial view of the Metro Prima MRT Station showing the pedestrian overhead bridge launching completed.
Construction of drainage and covered walkway in progress at the Metro Prima MRT Station Entrance 2.
Credits: mymrt.com.my.
📅 June 2020
Backfilling and compaction works in progress for the Multi Storey Park and Ride at the Metro Prima MRT Station site.
Water proofing at roof slab intermediate level in progress at the Metro Prima MRT Station site.
Credits: mymrt.com.my.
📅 March 2020
Aerial view of the Metro Prima MRT Station site showing the roof covering works in progress and mock up external painting completed.
Tiling installation works at Metro Prima MRT Station platform level in progress.
Credits: mymrt.com.my.
📅 January 2020
Aerial view of the Metro Prima MRT Station showing the roof covering and façade installation in progress.
Power rail installation at the Metro Prima MRT Station.
Credits: mymrt.com.my.
📅 November 2019
Aerial view of the Metro Prima MRT Station showing the installation of steel structure frames completed while installation of roof covering in progress.
View inside the Metro Prima MRT Station showing the completed installation of steel structure frames and installation of roof covering in progress.
Credits: mymrt.com.my.
📅 August 2019
Aerial view of the installation works for steel structure upper frame in progress at the Metro Prima MRT Station. Completed works for beam, slab and column at the platform level can also be seen.
Credits: mymrt.com.my.
📅 May 2019
Aerial view of the completed portal construction works at the Metro Prima MRT Station site.
Installation of blockwall in progress at the concourse level of Metro Prima MRT Station.
Credits: mymrt.com.my.
📅 January 2019
Ongoing construction works of beam, slab and column at the concourse and intermediate level of Metro Prima MRT Station.
Completion of segment S1 installation works for T-shape pier at the Metro Prima MRT Station site.
Credits: mymrt.com.my.
📅 December 2018
Ongoing Segmental Box Girder launching works at the Metro Prima MRT Station site.
Construction of beam, slab and column in progress for the Metro Prima MRT Station concourse level.
Credits: mymrt.com.my.
📅 November 2018
Aerial view of segmental box girder launching works of spans and permanent works for drainage at the Metro Prima MRT Station site.
Credits: mymrt.com.my.
📅 October 2018
Aerial view of bored piling works at the Metro Prima MRT Station site.
Installation of segmental box girder using sliding method at the Metro Prima MRT Station site.
Credits: mymrt.com.my.
📅 June 2018
Segmental Box Girder launching at the Metro Prima MRT Station site.
Completion of precast T-shape pier installation and Segmental Box Girder launching at the Metro Prima MRT Station site.
Credits: mymrt.com.my.
Hawk-eye View
Location of Metro Prima MRT Station and its surrounding area.
Credits: mymrt.com.my.